LNPA Pooling Subcommittee
February 1 – 3, 2000

In Attendance:

Mindi Patterson - TSE John Nakamura - TSE
Jean - TSE Beth Watkins - AT&T
Mike Panis - ESI Bob Angevine- GTE
Gustavo Hannecke _ MCIWorldcom Richard Bell - GTE
Clayton Tong - ESI Dave Garner - Sprint
Denise Best – MCIWorldcom
Marcel Champagne - Neustar
Donna Navickas - SBC

Neustar has agreed to provide certification of the Supplemental Test Plan. This step will be part of the R3.0 Project Plan and will be a prerequisite to beginning Turn Up testing in Region 1. Bob Angevine - GTE expressed a concern that perhaps these test runs should be observable by an SP. This team also reiterated that the Supplemental and Primary Test Plans should include ALL requirements. Appendix D will provide a trace matrix to ensure that all requirements are accounted for in one of the test phases.

The team asked that there be a specific go/no go Neustar decision based on their acceptance of R3.0 from their vendor. In addition, the number of defects and their severity levels should be identified to the customers at this time. Marcel Champagne advised the team that this decision and info would be provided on the 6/15/00 testing call. Note: The Chair of this subcommittee would like this date on the Release 3.0 Project Plan.

Bob Angevine once again raised the concern that the test plan is posted on the secure web site, Marcel Champagne stated that this can be done with the permission of the PEs.

Beth Watkins raised an issue about Disaster Recovery. We must have the ability to change over from one site to another (Chicago – Tarrytown) with replication turned on. It is important to validate this ability due to the fact we are changing to an object-oriented database (oodb) and there is higher risk with this implementation. The team agreed that a disaster recovery test must be performed in Region 1 on the test bed. Disaster Recovery testing will also be performed in the production environment (see Rollout Strategy). The expectation of this team is that on 7/3/00 both flavors of test bed releases will be available to SPs i.e. 3.0 OODB and 2.X Oracle. Both test beds will be available until all 8 regions have converted to R3.0 – OODB. Marcel Champagne will provide verification that Neustar can support this configuration.

David Heath Neustar validated that Neustar will provide required testing resources to support the rollout strategy.

All other testing and rollout strategies were worked out and documented in the "Release 3.0 Rollout Strategy".

 

EDR Migration

In our last meeting we discussed Release 3.0 Functional Requirements Specifications (FRS) Section 12 – "Migration for National Pooling". Mindi Patterson had pointed out previously that there would be no specific test cases in the Turn Up Test Plan to validate the migration plan requirements.

Test cases should have been added to 3.0 Test Plan. will add a migration test case(s). To be provided with next issue of test plan.

It had also been previously identified that Neustar will provide a pipe delimited conversion file for the pooling EDR conversion.

We will get a sample migration file prior to actual 3.0 installation. ( per Mindi same model as BDD Same as BDD format defined in 3.0 FRS )

Cindy Brown – Worldcom – raised a concern about LSMS that have inaccurate data on contaminated TNs. Subcommittee recommendation will include that SPs validate contaminated TNs prior to EDR migration. In addition, 3.0 conversion M&P should include that NPAC personnel validate that there are no "failed sp’s" in the existing pooled blocks.(for all 1k TNs, whether pooled or ported). It is recommended that this process be worked on an ongoing basis. One week prior to cutover NPAC personnel will ensure that no errant (failed sp’s) blocks exist.

In addition the Service Providers (SPs) validated that the desire is to convert to NPAC Release 3.0 region by region. This would not be national simultaneous cutover. It is acknowledged that SPs present in more than 1 region would have to possibly support both 1.4 and 3.0.

We identified 2 conversion options. They are as follows:

- Service Provider (SP) converts to EDR at time of NPAC Release 3.0 Installation

- SP converts to EDR at some point later than the NPAC 3.0 installation.

The following strawman processes were identified:

EDR Conversion with NPAC Install

  1. 2 week prior to install Neustar will provide a full BDD (current snapshot) of pooled production data in 3.0 format. This will allow SPs to test their ability to accept load this data.
  2. Starting Monday prior to conversion weekend there is to be a moratorium on all pooling activities i.e. add, delete or modify
  3. Friday evening before taking NPAC system down for 3.0 installation, Neustar will create migration files for EDR SPs of all existing pooled blocks in EDR block object format

4) SPs load migration file for EDR Block creation. After the "go/no go"(after complete installation) on weekend installation e.g. noon Sunday, decision for Release 3.0 is made they delete the pooled SVs SPs will require a minimum time frame (12 hrs) from the go/no go decision to complete their conversion. In this time frame the NPAC will not Deletion of pooled SVs will take place the week following installation implemented by each SP and will not be broadcast nor provided in the BDD file. This option will require a process to support "selective deletion". This process would require notification to SPs utilizing this option when an emergency modification/deletion of a pooled block is required in the week following R3.0 installation. This is needed to facilitate those SPs who are identified as EDR but have not yet deleted the pooled SVs from their LSMS. M&P will be needed for NPAC personnel to broadcast this info to all SPs and also for SPs to notify the NPAC if they intended modify an existing block.

NOTE: SP/Vendors need to identify if they can support individual delete mechanism.

It is also assumed that any subsequent porting activity during Week 2 of the moratorium will be BAU. SPs should review with their vendors.

  1. 1 week (5 business days) after R3.0 installation there is to be a moratorium on pooling adds, changes and deletions.

Post NPAC Install EDR Conversion

When an SP is converting from non-EDR to EDR, the SP obtains Bulk Data Download (BDD) file and updates their LSMS and downstream systems. This process is the same as the above described process with the exception of the moratorium periods.

In addition to the specific migration processes, the team discussed the testing requirements. Three requirements were needed for the migration file:

  1. A sample migration file is needed as soon as possible enabling the SP/vendors to validate file structure WHEN WILL SEE?
  2. A migration file is required for facilitating Turn Up testing. This is need by 7/1/00
  3. A complete migration file of the entire NPAC region is required to validate production data integrity.

Marcel Champagne, Lockheed will follow up to as to their ability to meet these dates.


lmclogo_s.gif (1902 bytes)

 

Send mail to Web Content with questions or comments about this web site.

Copyright © 1999 Neustar, Inc.
Last modified: May 15, 2000